Subdividing your block
in Melbourne: the basics

If you own a large block in Melbourne, splitting it into two or more lots can unlock a lot of value, whether you want to build a second home, sell part of the land or develop. Subdivision is a regulated process with several stages, and it usually takes a year or more. Here's how it works.
1. Check whether you can subdivide
Before you spend money on plans, check what could stop you:
- Zoning and overlays in the council's planning scheme, which set minimum lot sizes and other rules;
- Covenants on the title, such as a single-dwelling covenant, which can prevent subdivision altogether;
- Easements for drainage or sewerage that limit where you can build;
- Services, such as whether water, sewerage and power can reach a new lot.
Our guide to title searches explains how to spot covenants and easements. A conversation with the council's planning department early on is also worth having.
2. Engage a licensed surveyor
A licensed land surveyor prepares the plan of subdivision, showing the new lots, boundaries, easements and any common property. They usually manage the applications too, lodging them through SPEAR, the state's online subdivision system.
3. Get a planning permit
Most subdivisions need a planning permit from council. The application goes to referral authorities, such as the water corporation and electricity distributor, who can set their own conditions. Some simple subdivisions qualify for VicSmart, a faster assessment process. If neighbours can object, the permit may take longer.
4. Certification and meeting the conditions
Once the permit is issued, council certifies the plan of subdivision. You then have to meet the permit conditions, which commonly include:
- Connecting water, sewerage, power and drainage to each lot;
- Building crossovers and driveways;
- Paying a public open space contribution, often a percentage of the land's value, to council;
- Setting up an owners corporation if the lots share common property, like a driveway.
“The planning permit is the start, not the finish. Meeting the conditions is often where the time and money go.”
5. Statement of compliance and new titles
When every condition has been met, council issues a statement of compliance. The surveyor then lodges the certified plan with Land Use Victoria, which registers it and issues a separate title for each new lot. Only then can each lot be sold or mortgaged on its own.
Selling lots before the titles are issued
You can sell a lot before the plan is registered, but it's an off-the-plan sale with extra rules, including how long the buyer must wait for titles and what you must disclose. Get the contract prepared properly from the start. Our off-the-plan guide covers the buyer's side.
Costs and tax
Budget for surveyor and council fees, referral authority charges, service connections, the open space contribution, and legal and conveyancing costs. Subdividing to sell can also have tax consequences, including GST, income tax or capital gains tax, and windfall gains tax if the land is rezoned. Talk to your accountant before you start.
Where your conveyancer helps
- Checks the title for covenants, easements and mortgages before you start;
- Arranges your lender's consent to the plan, if there's a mortgage;
- Prepares owners corporation documents where needed;
- Prepares contracts and Section 32 statements to sell the new lots, including off the plan.
Start your subdivision on the right foot
We'll check your title, explain what could affect your plans and handle the legal work when you're ready to sell. Your first consultation is free.
Get a free consultationThe bottom line
Check zoning, covenants and easements first, then work with a surveyor through the planning permit, certification and permit conditions. Once council issues a statement of compliance, the new titles are registered and each lot can be sold. Allow plenty of time and budget for every stage.